Busy year 2016 for Port of Rauma

Port of Rauma Rauman Satama December 2016

 

Progress with container terminal extension
Over 20 M€ investment got started at Port of Rauma in April 2016. During the 8 months we have seen a lot of dredging,
rock blasting and making of 70 pieces of huge quay elements. Project will continue in 2017.

Container terminal extension 2016 (video)

 

Channel deepening continues
In April 2016, another huge project got started. Rauma channel deepening is in progress by Port of Rauma Ltd
& Finnish Transport Agency. The 41 M€ project will be finished by the end of 2017.